We are proud to have co-hosted the topping-off with prime contractor SES Electrical LLC event for the 54,000 sq. ft. pre-Engineered Panelized Modular Relocatable Buildings (PPMRBs) at Davis Monthan AFB. This event marked a significant milestone for the AMARG leadership team, SEL, PPS, and our partners, celebrating the installation of the final structural piece for the impressive 155’ C-130 mega door. It represents a pivotal moment in bringing AMARG’s vision of expanding operations from Hill AFB to Davis Monthan AFB to fruition.

From award in Sept ’23 to final steel in May ’25, this project moved fast. We wrapped design in 9 months, broke ground in July, and had steel up by November. Delivering a 54,000 sq. ft. TAMS hangar with an integrated bead blast booth in just 10 months is a huge win for the team—tight coordination, hard execution, real results.

Proud to be part of this team—SES Electrical LLC, Dogwood Industries, Navigator International, LLC, Kezlo Group, LLC, and Aerospace Facilities Group, Inc. —whose collaboration made this milestone possible!