Permian Basin 400 MWH BESS

$8M | Peyote, TX | Jupiter Power

PPS provided electrical services in support of two 200MWH BESSs in Permian Basin region of Texas, constructed concurrently. Project required: loading of ~$140M of lithium-ion batteries weighing in total 7.2M pounds; construction for all medium voltage circuits from customer point of interconnect at substation riser, along with inverters, auxiliary transformers, and BESS containers; and final DC connection and commissioning.