5 Site BESS

$1M – $5M | Texas | Key Capture Energy

Scattered across East and West Texas, these five 9.9MW sites provided additional ERCOT grid resiliency and served as an early proving ground for BESS implementation in the ERCOT market.

UNIQUE ATTRIBUTES: Topography variations across all five sites presented each of their own unique challenges from the requirement of GREP ground preparations in East Texas, to the use of Rock Saws in the rock-laden West Texas region. PPS prevailed in working with the GC and client to provide a successful, on time delivery of all five sites and prompt return on equity to all stakeholders.